City of Houma Electric and Gas Update / End of Day / September 6, 2021
09/06/2021 07:00 PM
City of Houma Electric and Gas update for end of day on Monday, September 6, 2021.
ELECTRIC
Damage assessments have reported a total of 194 broken poles, 494 leaning/down poles, 474 locations of down/broken primary and secondary wires, 107 damaged transformers, 322 damaged crossarms, 890 damaged insulators and 105 damaged streetlights.
As of 09/06/2021, 226 of the accessed poles have been repaired or replaced and are back in working condition pending Entergy’s transmission completion on Wednesday, 9/8/2021.
115 KV Transmission - 100% complete with damage assessment.
- 3 broken poles
 - 2 leaning/down poles
 - 6 different locations of down/broken primary and secondary wires
 - 19 insulators damaged
 - 4 damaged crossarms
 - 3 damaged transformers
 
Repaired 11 substations.
- 2.5 miles of 115KV and 22 Miles of 34.5KV.
 
Cummins 3 feeder – 10% complete with damage assessment.
- 4 broken poles
 - 2 leaning/down poles
 - 4 different locations of broken primary wires
 - 7 damaged insulators
 - 4 damaged crossarms
 
Dumas 1 feeder -100% complete with damage assessment.
- 6 broken poles
 - 19 leaning/down poles
 - 27 different locations of down/broken primary and secondary wires
 - 7 damaged crossarms
 - 2 damaged transformers
 - 21 damaged insulators
 
Dumas 2 feeder – 100 % complete with damage assessment.
- 3 leaning/down poles
 - 1 broken secondary wire
 
Loop 1 – 100% complete with damage assessment.
- 1 broken pole
 - 6 leaning/ down poles.
 - 3 different locations of down/broken primary wire
 - 6 damages crossarms
 
Loop 3 – 100% complete with damage assessment.
- 24 broken poles
 - 36 leaning/down poles
 - 79 different locations of down/broken primary and secondary wire
 - 23 damaged cross arms
 - 9 damaged transformers
 - 4 damaged streetlights
 - 35 damaged insulators
 
McKinley 1 feeder – 100% complete with damage assessment.
- 3 broken poles
 - 12 leaning/down poles
 - 27 different locations of down/broken primary and secondary
 - 20 damaged insulators
 - 8 damaged crossarms
 - 3 damaged transformers
 - 3 damaged streetlights
 
McKinley 2 feeder – 100% complete with damage assessment.
- 4 leaning/down poles
 - 3 different locations of down/broken primary and secondary wire
 - 1 damaged transformer
 
McKinley 3 feeder – 100% complete with damage assessment.
- 2 broken poles
 - 1 leaning/down poles
 - 13 different locations of down/broken primary and secondary wire
 - 4 damaged insulators
 - 1 damaged crossarm
 - 1 damaged streetlight
 
Norman Sub – 100% complete with damage assessment.
- 50 broken poles
 - 76 leaning/down poles
 - 202 different locations of down/broken primary and secondary wire
 - 552 damaged insulators
 - 157 damaged crossarms
 - 29 damaged transformers
 - 7 damaged streetlights
 
Plant Road 1 feeder – 100% complete with damage assessment.
- 2 broken poles
 - 1 leaning/down poles
 - 16 different locations of down/broken primary and secondary wire
 - 16 damaged insulators
 - 2 damaged crossarms
 - 3 damaged transformers
 - 7 damaged streetlights
 
Sherwood 1 feeder – 50% complete with damage assessment. Will be 100% complete by end of day 09/06/2021.
- 3 broken poles
 - 11 different locations of down/broken primary and secondary wire
 - 7 damaged insulators
 - 4 damaged crossarms
 - 1 damaged transformer
 - 3 damaged streetlights
 
Sherwood 2 feeder – 100% complete with damage assessment.
- 12 broken poles
 - 11 leaning/down poles
 - 38 different locations of down/broken primary and secondary wire
 - 36 damaged insulators
 - 11 damaged crossarms
 - 7 damaged transformers
 - 4 damaged streetlights
 
Six Street feeders 1&2 – 100% complete with damage assessment.
- 19 broken poles
 - 73 leaning/down poles
 - 64 different locations of down/broken primary and secondary wire
 - 38 damaged insulators
 - 22 damaged crossarms
 - 14 damaged transformers
 - 4 damaged streetlights
 
Southdown 1 feeder – 99% complete with damage assessment. Will be 100% complete by end of day 09/06/2021.
- 5 broken poles
 - 24 leaning/down poles
 - 24 different locations of down/broken primary and secondary wire
 - 4 damaged insulators
 - 3 damaged crossarms
 - 3 damaged transformers
 - 3 damaged streetlights
 
Southdown 2 feeder – 100% complete with damage assessment.
- 5 broken poles
 - 30 leaning/down poles
 - 15 different locations of down/broken primary and secondary wire
 - 24 damaged insulators
 - 9 damaged transformers
 - 10 damaged crossarms
 
Southdown 3 feeder – 100% complete with damage assessment.
- 14 broken poles
 - 81 leaning/down poles
 - 125 different locations of down/broken primary and secondary wire
 - 20 damaged insulators
 - 17 damaged crossarms
 - 8 damaged transformers
 - 7 damaged streetlights
 
Southdown 4 feeder – 100% complete with damage assessment.
- 7 broken poles
 - 8 leaning/down poles
 - 25 different locations of down/broken primary and secondary wire
 - 7 damaged insulators
 - 5 damaged crossarms
 - 2 damaged transformers
 - 3 damaged streetlights
 
Plant Road 2 feeder – 15% complete with damage assessment. Will be 100% complete by end of day 09/06/2021.
- 3 leaning/down poles
 - 6 different locations of down/broken primary and secondary wire
 - 2 damaged insulators
 
Southdown Sub – 100% complete with damage assessment.
- 28 broken poles
 - 28 leaning/down poles
 - 85 different locations of down/broken primary and secondary wire
 - 16 damaged insulators
 - 34 damaged crossarms
 - 8 damaged transformers
 - 10 damaged streetlights
 
GAS
- Gas leaks since 8/30/21: 66
 - Turn Offs since 8/30/21: 142
 - Locates since 8/30/21: 240
 
Special thanks to Ernest Brown and his team for working so hard to get us this information for our residents! We know the road ahead is long but we are in this together, Terrebonne!